Wednesday, March 24, 2010

Frame Done -- In 2 days

Hi All..
Frame is done... progress payment is in my hands.

Only took them 2 days to erect the frame.. so I have made an appointment with the SS and building inspector to have a look.

Going really quickly now!


The Backyard^^

Entry Hall ^^


^^Kitchen




^^ Front



^^Lounge Room












^^ Study










Monday, March 22, 2010

Slab

The slab was poured Monday 15th March.












Sunday, March 21, 2010

Waffle Slab

Waffle pod. Only took a few days to construct..













Site Start and Scrape


Site start commenced 3rd March 2010! Site was scraped, cut and plumbing was installed, along witht the power and water.